Can you tell me the necessary settings required for a meterial Inspection - Purchased as raw material, where some MICs are checked with every lot and some are checked once a month. In a month there could be one lot or several lots (10 or 20 or 0 etc.) With best regards, Sukhbir P Mittal You create necessary MICS. Then assign MICS to Inspn plan in QP01. For those MICS which need inspn every lot (critical characs chk),do not enter a dyn mod rule. For those that need skip type inspn, say inspect first
lot , if ok then skip rest 29 lots (Asumption 1 lot per day,so 30 lots
a
Also plan header need to be populated for dyn mod level at charac level & rule. Pl. try this out & let us know. Regards, Krishna